After Molding

  • After Molding first and foremost thing is CURING. First four or five days, roof will consume more water. So you should be able to provide water properly without fail
  • Usually water will be stored after molding on top of roof.
  • During this process if there are any pillars leave 9″ space around pillar.
  • Place left over pillar will provide a room for pillar boxes. So that without disturbing curing process, workers can start working on pillars for another floor. This will save Mason time also

Few other people construct directly one course of the brick where ever they planned to construct wall as shown in the below picture that will save one day effort and material also. Observe below picture for more details